Using the crane in the picture, steel support beams were placed for the roof over the new kitchen space. Appearing to be painting, the workers were applying a moisture barrier on the blocks. Insulation and bricks will still be added to the exterior of the new area.
Tuesday, July 29, 2008
GLHS Creek Crossing work
Tuesday, July 22, 2008
Delta Center progress
The new classrooms at Delta Center have their interior walls built.
The parking area, under construction, at Delta Center is viewed from across Canal Road. A new island in the parking lot has been created.
- New parking lot organization at Delta Center –
The new Delta Center parking area will require everyone to learn about changes in the traffic flow. - The north end of the parking lot will be for parents dropping off their students and for parent parking.
- The south end of the parking lot will have a lane for buses only. Staff will also park at the south end of the parking lot.
Holbrook parking area and A/C system progress
The area next to the current parking lot is prepared for a paved addition of approximately 36 parking spaces.
In classrooms and in the kitchen area, workers install the new A/C system. Greenwood, Neff and Delta Center elementaries are having the same A/C work done. (Willow Ridge and Wacousta have A/C systems in place.)
GLHS - new classrooms being built at SE corner
Thursday, July 17, 2008
Neff parking area
Friday, July 11, 2008
Projects Advance in July
At Greenwood Elementary, old univents are removed from classrooms to prepare for new vertical air conditioning units. After this summer, A/C will be in all GLPS classrooms. The new units will be quieter (better for studying), more energy efficient and provide a better distribution of air in classrooms.
Ceiling work at Delta Center, Greenwood, Holbrook and Neff includes installing chilled water lines for the A/C system and some duct work.