Thursday, August 28, 2008

New Holbrook parking area


Parents who drive to Holbrook elementary - please use the new entry on Schoolcraft Street. The Jones Street drive will be for exits only. Thank you!

Wacousta Kitchen and Playground






The kitchen at Wacousta elementary is nearly finished. The construction is complete and the appliances are in place. Once the final check process is complete the serving line will open.
The new playground equipment is ready for the children to start school on Tuesday, September 2.

Wednesday, August 20, 2008

GLHS Creek Crossing



The Grand Ledge High School creek crossing is being constructed. In the pictures, the crane lifts precast pieces into place to form the bridge support.

Wednesday, August 13, 2008

Greenwood's cabinets and A/C units installed


In Greenwood classrooms the new vertical A/C units replaced the old unit ventilators. In the wall space left over from the old ventilators, cabinets were installed. The teachers will be able to use the space to store classroom materials.

Delta Center projects move onward




At Delta Center the new classrooms have ceilings and windows. The air conditioning units are being installed throughout the building.

Classroom construction at GLHS


















Work on the four new classrooms at the high school continues. All schools will open September 2. The goal is to have the new projects completed as soon as possible. In the event that the new projects are not completed by the beginning of school, student education and services will not be affected.

Neff A/C units installed, carpet on floors




The vertical, air conditioning units are quieter and better for studying. They are also energy efficient and provide a better distribution of air in classrooms.
After the A/C units were installed, worn carpeting was replaced with new.

Tuesday, August 5, 2008

Delta Center Entrance


The parking area at the south end of Delta Center's traffic entrance is nearly ready for asphalt. The north end has been paved.

New windows at Delta Center

















New windows are being installed at select locations in Delta Center, Greenwood, Holbrook, Neff and Wacousta elementary schools. The windows pictured above are at Delta Center. The tinting will help to cut down on bright glare and when opened they provide a fire escape route. They have double panes of glass, making them energy efficient.


Holbrook Parking Area Takes Shape



Cement is poured at Holbrook's parking area.